Case Number 11987
Request Date 07/07/2026
Completion Date 07/08/2026

 

Details of the Request

Under the Freedom of Information Act 2000, and, where the information concerns the trust's buildings or estate, the Environmental Information Regulations 2004 (EIR), I request the recorded information set out below. Please treat each question under whichever regime applies.

Where a question asks about future plans, please provide only information the trust currently holds in recorded form, such as an approved business case or an entry in the capital programme. Where no time period is given, the most recent available figure is fine.

If answering any single question would exceed the cost limit under section 12 of the Act, please answer the remaining questions and tell us which you have set aside, so we can refine it. If any answer is already published, a link under section 21 is sufficient.

 

1. Operating Theatres: Capacity and Condition

  1. As at the most recent date, how many operating theatres does the trust have in use? Please break this down by type: standard, laminar-flow, day-case or procedure, and hybrid (with integrated imaging).
  2. For each operating theatre, please give the year it was built or last fully refurbished (a full refurbishment includes a new HVAC, that is, heating and ventilation, system).
  3. Does the trust hold an estate register or list of its operating theatres? If so, please provide it or its key fields.
  4. What was the average operating-theatre utilisation rate over the most recent twelve months (for 1xample, the percentage of available session time used)?
  5. How many operating theatres, if any, are currently out of use or operating under restriction, and for what recorded reason?    

 

2. Surgical Hubs

  1. Does the trust operate an elective surgical hub (a unit given over to planned surgery with ring-fenced theatres and staff)? If yes, please give the year it opened and the number of theatres it contains.
  2. Is any such hub accredited under the GIRFT Elective Hub Accreditation programme?
  3. Are there approved or planned schemes to create or expand a surgical hub within the next five years? If so, please give a brief description, the number of theatres, and the expected date.

 

3. Endoscopy and Diagnostics

  1. How many endoscopy procedure rooms does the trust have in use?
  2. At the most recent date, what is the size of the endoscopy waiting list and the longest wait, if not already published?
  3. Are there approved or planned schemes to add endoscopy or community diagnostic capacity within the next five years? Please describe briefly, with expected dates.

 

4. Central Sterile Services Department (CSSD)

  1. Is the trust's Central Sterile Services Department (CSSD) provided in-house or outsourced? If outsourced, to which provider, where recorded?
  2. In what year was the main CSSD facility built or last significantly refurbished (a significant refurbishment includes replacing essential components such as sterilisers)?

 

5. Endoscope Decontamination

  1. Is the trust's endoscope decontamination provided in-house or outsourced? If outsourced, to which provider, where recorded?
  2. In what year was the main endoscope decontamination facility built or last significantly refurbished (a significant refurbishment includes replacing essential components such as AERs, the machines that clean endoscopes)?
  3. In the last three years, has any decontamination or sterilisation facility had unplanned downtime that required temporary or contingency arrangements? If so, please describe briefly.

 

Details of the Response

1. Operating Theatres: Capacity and Condition

1a. As at the most recent date, how many operating theatres does the trust have in use? Please break this down by type: standard, laminar-flow, day-case or procedure, and hybrid (with integrated imaging).

Ashford Theatres

  • 8 Main Theatres - out of which 6 are laminar flow and 2 are standard theatres
  • 2 Additional Theatres for Ophthalmic procedures - out of which 1 is General Anaesthesia capable and one is only Local Anaesthetic procedures
  • 1 Day surgery theatres in Day Surgery Unit.
  • Additional Treatment room for Chronic Pain Procedure in Day Surgery

 

St Peter’s Theatres

  • 7 Main Theatres - out of which 2 are laminar flow
  • 1 Urology Theatre
  • 2 Obstetric Theatres

 

1b. For each operating theatre, please give the year it was built or last fully refurbished (a full refurbishment includes a new HVAC, that is, heating and ventilation, system).

  • Ashford theatre 1,3,6 built in 2021
  • Ashford theatre 2 refurbished 2022
  • Ashford theatre 7&8 built in 2025
  • Ophthalmology Theatre 1&2 Built 2025
  • Remaining theatres are part of the theatre refurbishment plan.
  • St. Peters T6 Ventilation plant replaced 2014
  • St. Peters T3&4 Ventilation plant replaced 2016
  • St. Peters T1&2 Ventilation plant replaced 2018

 

1c. Does the trust hold an estate register or list of its operating theatres? If so, please provide it or its key fields.

  • As provided above

 

1d. What was the average operating-theatre utilisation rate over the most recent twelve months (for 1xample, the percentage of available session time used)?

The capped theatre utilisation rate (last recorded in July 2026) was 77.2%.

 

1e. How many operating theatres, if any, are currently out of use or operating under restriction, and for what recorded reason?    

  • Ashford - 1 Day Surgery Theatre is closed due to Ventilation noncompliance
  • St Peter’s
    • Theatre 6 layup room is closed (due to ventilation noncompliance - insufficient air changes)
    • Urology Theatre layup room is closed (due to ventilation noncompliance - insufficient air changes)
    • Theatre 1 & 2 shared layup room is closed (ventilation noncompliance - air pressure is lower than it should be)

 

2. Surgical Hubs

2a. Does the trust operate an elective surgical hub (a unit given over to planned surgery with ring-fenced theatres and staff)? If yes, please give the year it opened and the number of theatres it contains.

Elective Surgical Hub to deliver Orthopaedic Procedure was opened in 2026 with ring fenced post operative surgical ward. Currently 5 Theatres per day are dedicated for Orthopaedic Elective surgery

 

2b. Is any such hub accredited under the GIRFT Elective Hub Accreditation programme?

Trust achieved GIRFT Elective Hub Accreditation for Orthopaedic Elective Surgery in 2026

 

2c. Are there approved or planned schemes to create or expand a surgical hub within the next five years? If so, please give a brief description, the number of theatres, and the expected date.

There are no approved or planned schemes.

 

3. Endoscopy and Diagnostics

3a. How many endoscopy procedure rooms does the trust have in use?

3

 

3b. At the most recent date, what is the size of the endoscopy waiting list and the longest wait, if not already published?

Total size is 2170, longest wait is 40 weeks

 

3c. Are there approved or planned schemes to add endoscopy or community diagnostic capacity within the next five years?

Yes provision for endoscopy at Ashford is progressing and is hoped to be completed by the end of 2026 followed by expansion and refurb of St Peters, no timescale as yet.

 

4. Central Sterile Services Department (CSSD)

4a. Is the trust's Central Sterile Services Department (CSSD) provided in-house or outsourced? If outsourced, to which provider, where recorded?

In-house

 

4b. In what year was the main CSSD facility built or last significantly refurbished (a significant refurbishment includes replacing essential components such as sterilisers)?

Full refurbishment of Cleanroom in 2023, Washer-Disinfectors and Sterilsers replacement programme commenced in the last 5 years..

 

5. Endoscope Decontamination

5a. Is the trust's endoscope decontamination provided in-house or outsourced? If outsourced, to which provider, where recorded?

In-house

 

5b. In what year was the main endoscope decontamination facility built or last significantly refurbished (a significant refurbishment includes replacing essential components such as AERs, the machines that clean endoscopes)?

2010, Equipment replacement programme commenced with 2 AERs in June 2026

 

5c. In the last three years, has any decontamination or sterilisation facility had unplanned downtime that required temporary or contingency arrangements? If so, please describe briefly.

RO water failure

 

 